90-Day Implementation Roadmap

Roadmap Overview

Day 30
Machinery Order Deadline (Critical)
Days 1-90
Foundation Phase
210 days
Total Time to Production
Q2-Q3 2026
Production Launch Target

Phase 1: Foundation & Financing (Days 1-30)

Days 1-30: $820k Investment
Days Activity Owner Deliverable Cost
1-7 Legal entity formation (FZ + Mainland) Legal Counsel (Al Tamimi) Trade licenses issued $120k
5-14 Emirates Development Bank application CFO (Interim) Loan approval secured $15k
7-21 Facility site selection & lease negotiation CEO + Operations Consultant KEZAD lease signed $30k
14-28 EUR/AED forward contract hedging CFO + Bank Currency risk eliminated $22k
30 Machinery deposit & order placement CEO + Procurement Bühler, Loring orders confirmed $585k

Phase 2: Facility Development (Days 31-90)

Days 31-90: $415k Investment
Days Activity Owner Deliverable Cost
31-60 Rebranding agency engagement CEO + Marketing Lead Brand strategy & design approved $200k
31-75 Facility design & construction planning MEP Engineers + Architects Construction ready plans $30k
45-90 ERP system implementation (Odoo) IT Consultant System configured & tested $20k
60-90 Key staff recruitment HR + CEO GM, Production Mgr, QC Mgr hired $40k
75-90 Facility construction initiation General Contractor HVAC, utilities, floor work started $130k

Phase 3: Market Entry Preparation (Days 91-180)

Days Milestone Key Activities Budget
91-120 Facility construction completion HACCP infrastructure, clean rooms, utilities $200k
120-150 Interim product sourcing "Packed in UAE" inventory for early market testing $80k
120-160 Compliance documentation HACCP manuals, Halal applications, licenses $60k
150-180 Machinery installation & commissioning Equipment delivery, setup, trial runs €1.26M
160-180 Staff training & HORECA outreach Production training, initial account meetings $65k

Phase 4: Production Launch (Days 181-210)

Commercial Production Authorization

Critical Path Analysis

Critical Path Items (Cannot Be Delayed)

  1. Day 14: EDB Loan Approval - Required for Day 30 machinery deposit
  2. Day 30: Machinery Orders - 6-9 month lead time drives entire timeline
  3. Day 90: Facility Construction Start - Must complete before equipment delivery (Day 150)
  4. Day 150: HACCP Audit - Required for production authorization
  5. Day 180: Equipment Commissioning - Must complete for Day 210 launch

Warning: Any delay in Day 30 machinery order pushes launch to Q4 2026, missing optimal market entry window.

Risk Mitigation - Critical Path

Risk Impact Probability Mitigation
EDB loan delay High (blocks machinery order) Low (15%) Parallel bridge financing arrangement with local bank
Machinery delivery delay High (pushes launch 2-3 months) Medium (30%) Penalty clauses in supplier contracts, alternative suppliers identified
HACCP certification delay Medium (delays production) Low (10%) Pre-audit consultants, documentation ready by Day 120
Key staff recruitment failure Medium (operational readiness) Medium (25%) Multiple candidates in pipeline, recruitment agency engaged

Resource Allocation

Phase 1: 90-Day Implementation Team

Full-Time Resources

  • CEO: Full-time commitment (Days 1-90)
  • CFO (Interim): Part-time consultant, $10k/month

External Partners

  • Legal Counsel: Al Tamimi, $50k retainer
  • Brand Agency: WonderEight, $200k project
  • ERP Consultant: Odoo Partner, $20k implementation

Phase 2: Year 1 Operations Team (15 Headcount, $900k/year)

Production (8 staff, $360k)
  • Production Manager: $70k
  • Chocolate Technician: $45k
  • Coffee Roaster: $45k
  • Production Operators (3×): $90k
  • Packaging Staff (2×): $50k
Quality & Compliance (3, $145k)
  • QC Manager: $65k
  • QC Technician: $40k
  • Food Safety Officer: $40k
Commercial & Admin (4, $220k)
  • Sales Director: $80k
  • HORECA Sales Rep: $50k
  • Marketing Coord: $45k
  • Finance/Admin: $45k

Hiring Timeline

Budget Deployment Timeline

Phase Timeline Investment Cumulative % of Total
Phase 1: Foundation Days 1-30 $820k $820k 23%
Phase 2: Development Days 31-90 $415k $1,235k 35%
Phase 3: Market Entry Days 91-180 $1,695k $2,930k 84%
Phase 4: Working Capital Days 180-270 $570k $3,500k 100%

Board Decision Point

Immediate Action Required: Board approval by November 30, 2025 to initiate Day 1 activities December 1, 2025.

Consequence of Delay: Each month of delay pushes production launch and extends breakeven timeline, reducing Year 1-2 revenue by ~$400k per month of delay.